Revitalization Project: Construction Phases

photos buttonPhase One is underway in the lower level, which will remain closed to the public. Repairs will address the HVAC, elevator, lighting, and other infrastructure needs. When completed, the lower level will house updated areas for children and teens as well as audio-visual materials.

renovation plans for parkside, lower level, of the library

Phase 1 childrens and AV area plansPhase 1 teen and office area plans

 

 


Phase Two construction, expected to begin in the spring of 2021, will renovate portions of the main level to house the Community Room, a new conference room, ADA-compliant restroom, seating area, and adult computer area. The work on the main level will not involve the historic restorations completed in 2018.

renovation plans for streetside, upper level, of the library

Phase 2 adult collection and computer area plansPhase 2 community room periodicals area plans